Construction Update - Week of September 5 - 8


Hinckley Street
  • Ludlow Construction will continue installing new drainage between Warner Street and Winslow Ave.
  • The intersection of Warner Street may be closed on Tuesday, September 5 during normal working hours (7 a.m. - 3 p.m.) Traffic on Hinckley Street will be limited to local traffic only.  Motorists should expect delays and encouraged to seek alternate routes. 
  • The work on this road includes the replacement of water, sewer and drainage utilities, a new drainage outfall off Riverside Drive, new sidewalk, roadway reclamation and repaving, and a raised crosswalk across Nonotuck Street.    
Pleasant and Holyoke Streets
  • Geoge Cairns and Sons Construction will be excavating and  installing sheet pile bracing behind the former Northampton Lumber site in preparation for installation of a large drainage culvert.
  • The work consists of realigning a section of drainage culvert behind the former Northampton Lumber site and across Holyoke Street in order to accommodate the redevelopment of the site.
Pleasant and Williams Streets and Hockanum Road Gas Work
  • Columbia Gas is replacing gas main and services along these routes. Work will continue through the summer. 
Day Avenue Ave/North Maple/North Farms
  • Caracas Construction will continue with the installation of the new water main in North Farms Road this week. One-lane traffic will be maintained, but motorists should expect delays or seek alternate routes, if possible.  Access for local residents will be maintained.  Temporary road closures may be required.
  • No work is expected on Day Avenue this week. The road will be open for use. Once work is complete on North Maple Street and North Farms Road, Caracas will return to Day Avenue to complete road work at that location.  
Audubon Road
  • No work is expected on Audubon Road this week. Borges Construction is waiting for the new culvert to be fabricated. Delivery and installation of the new culvert is anticipated to begin the week of September 11.
  • The work on this road includes replacing water and drain lines and a box culvert followed by reclaiming and repaving of the roadway from the center of Leeds to near house #200.
Contact the DPW at 587-1570 or dpwinfo@northamptonma.gov if you need more information.