Construction for the week of 11-13-17 Weather Permitting


Construction for the Week of 11-13-17 Weather Permitting

Hinckley Street  
  •  Ludlow Construction is not planning to work on Hinckley Street this week.  When they do resume, they will continue constructing the new water system on Hinckley Street between Riverside and Warner Street.  Expect temporary road closures on Hinckley Street, and unanticipated water shutdowns.
  • The work on this road includes the replacement of water, sewer and drainage utilities, a new drainage outfall off Riverside Drive, new sidewalk, roadway reconstruction and repaving, and a raised crosswalk across Nonotuck Street.
Pleasant and Holyoke Streets
  • George Cairns and Sons Construction will continue installing a large drainage culvert in Holyoke Street and the Lumberyard property. Holyoke Street will be CLOSED TO THROUGH TRAFFIC from Pleasant Street to Hawley Street until late November or early December. Access for local residents and businesses will be maintained.
  • The work consists of realigning a section of drainage culvert behind the former Northampton Lumber site and across Holyoke Street in order to accommodate the redevelopment of the site.

Day Avenue, North Maple Street & North Farms Road
  •  Caracas Construction will be reconstructing the sidewalk and working on driveway aprons on Day Avenue this week. Work for the season is anticipated to be nearly complete this week. Final paving and restoration will occur next spring. The roadway will be CLOSED TO THROUGH TRAFFIC during work hours. Motorists should seek alternate routes.  Access for local residents and emergency vehicles will be maintained.
  • No work is expected on North Maple Street and North Farms Road this week, and the work is substantially complete except for the replacement of a section of drainage pipe near the intersection with Mountain Street. The road will be open for use.
Audubon Road

  •  Borges Construction will be raising structures doing miscellaneous restoration work on Audubon Road during this week. Work for the season is anticipated to be complete this week. Final paving and restoration will occur next spring. The roadway will be CLOSED TO THROUGH TRAFFIC during work hours. Access for local residents will be maintained. Emergency vehicles and school buses will be allowed to pass through the site. Motorists should seek alternate routes. The road will be re-opened after work hours for all vehicles.
  • The work on this road includes replacing water and drain lines and a box culvert followed by reclaiming and repaving of the roadway from the center of Leeds to near house #200.
Reservoir Road
  • Davenport Trucking will continue repairs to rehabilitate the channel and stream bank erosion just downstream of the Lower Roberts Meadow Dam. The roadway will be open, but motorists should use caution and be aware of heavy construction vehicles entering and leaving the site.
  • The work requires bypass pumping of stream flows in order to complete stream channel and bank rehabilitation. Weather permitting, the work is anticipated to be substantially complete this construction season.