Friday, August 17, 2018

For the week of 8-24 Weather Permitting



For the week of 8-24-18Weather Permitting

Pothole Update

  • This week the DPW crews repaired potholes on Allen Place, Church Street, Winslow Avenue, Elm Street, Berkshire Terrace, Langworthy Road and Crestview Drive.
  • The largest potholes are filled first to alleviate hazards to motor vehicles. As hazards arise and are identified they will be addressed. To report a pothole please visit: http://northamptonma.gov/requesttracker.aspx
  • Street Sweeping in Ward 7 is now complete. Ward 6 is currently in progress.

Hinckley Street
  • Ludlow Construction will be working along the full length of Hinckley Street this week.
  • Starting Wednesday, August 22nd, 2018, Final Paving will occur from South Main Street to Riverside Drive, including work at the intersections of South Main Street, Nonotuck Street, Winslow Avenue, Warner Street and Riverside Drive. THERE WILL BE NO PARKING ALLOWED ON HINCKLEY STREET OR NEAR THE INTERSECTIONS MENTIONED ABOVE, AND VEHICLES WILL BE TOWED.
  • Please park outside of the posted NO PARKING WORK ZONE. Traffic Police will be on site to keep vehicles out of the work area. If you are a Resident of Hinckley Street, please move your vehicle outside of the work zone by 7:00 AM on Wednesday, August 22, and Thursday, August 23 as necessary.
  • Other work includes finish paving of sidewalks, driveways, and other incidental locations.
Chesterfield Road at Kennedy Road - Upper Roberts Meadow Reservoir Dam

  • SumCo Eco-Contracting, LLC has removed approximately 20 vertical feet of the dam with approximately 10 vertical feet remaining to be removed. Additional removal of the dam will not occur until after rain events mobilize sufficient sediment in the impoundment downstream. SumCo will be on site to monitor sediment movement weekly and after rain events but has otherwise demobilized from the site.
  • The project will remove the Upper Roberts Reservoir Dam to restore the Roberts Meadow Brook stream channel to its natural course.
Chesterfield Road -

  • Palmer Paving, through their subcontractor CNA, will be installing water services on Chesterfield Road.
  • Detours will be in place around the construction zones from Chesterfield Rd and Spring St through Dimock St and possibly Reservoir Rd, Main Street Leeds and Spring Street.
  • The project includes replacement of the water line, drainage improvements and reconstruction of the roadway.

Downtown Paving – Pleasant Street, Hampton Avenue, Wright Avenue, Cooke Avenue and Fulton Avenue Downtown Paving – Pleasant Street, Hampton Avenue, Wright Avenue, Cooke Avenue and Fulton Avenue

  • Warner Brothers LLC and their subcontractor Caracas Construction Corp. will continue work on drainage improvements for Hampton Ave and Wright Ave this week. Traffic on these streets may be restricted to one lane at times, expect some delays.
  • The project includes re-paving of Hampton Avenue, Wright Avenue, Cooke Avenue, Fulton Avenue and Pleasant Street (from Main Street to Hockanum Road).

Pleasant Street

  • Columbia Gas will be installing new gas services on Pleasant Street. Motorists should EXPECT DELAYS and seek alternate routes if possible. The work is anticipated to take several months to complete.

Clement Street Bridge

  • N.E.L. Corporation continues installing temporary truss supports and replacing lower chord truss members. Anticipated project completion is in September. Actual reopening of the bridge will depend on MassDOT approval of the completed work.
  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction.

Rocky Hill Road (Route 66) - Drain Repair opposite entrance to House of Corrections

  • Geeleher Enterprises has completed the emergency repairs. Seeding has been completed and vegetation growth is expected.

Monday, August 13, 2018

Temporary Closure of Northampton Bikeway August 14, 2018

Tuesday, August 14, 2018 the Department of Public Works will be working on the King Street Brook and the sedimentation basin located at the end of the Northampton Bikeway by Stoddard and State Streets at the rear of Stop and Shop.

Bikeway users should take notice that the Bikeway will be closed to all bike and pedestrian traffic  between Adare Place and Stoddard Street.

Please be advised that there will be heavy equipment traveling up and down the Bikeway at the closure location.  For their own safety, all users of the Bikeway will be turned back at the closure locations.  Police details will be present.

Thank you for your patience and understanding during this construction process.  The blog will be updated as needed during this project.

Friday, August 10, 2018

Week of 8-13-18 Weather Permitting



For the week of 8-13-18 Weather Permitting

Pothole Update
  • This week the DPW crew repaired potholes on State Street Extension, Washington Avenue, Corticelli Street, North Main Street by the Roundabout, Mountain Street by Carolyn Street, Rustlewood Ridge, Birch Lane, Allen Place and Burts Pit Road Extension.
  • The largest potholes are filled first to alleviate hazards to motor vehicles. As hazards arise and are identified they will be addressed. To report a pothole please visit: http://northamptonma.gov/requesttracker.aspx
Hinckley Street
  • Ludlow Construction will not be working on Hinckley Street for most of the coming week (Aug 13th – 17th). They may be conducting minor sidewalk work and clean-up activities at times.
Chesterfield Road at Kennedy Road - Upper Roberts Meadow Reservoir Dam
  • SumCo Eco-Contracting, LLC has removed approximately 20 vertical feet of the dam with approximately 10 vertical feet remaining to be removed. Additional removal of the dam will not occur until after rain events mobilize sufficient sediment in the impoundment downstream. SumCo will be on site to monitor sediment movement weekly and after rain events but has otherwise demobilized from the site.
  • The project will remove the Upper Roberts Reservoir Dam to restore the Roberts Meadow Brook stream channel to its natural course.

Chesterfield Road – Spring Street to Shepherds Hollow Road
  • Palmer Paving and their subcontractor C&A will not be on site for Monday and Tuesday. C&A plans to replace water service connections on Wednesday, Thursday and Friday. The road will be closed to through traffic on these days. Homeowners may experience water shutoff for up to an hour, as each water service connection is replaced.
  • Detours will be in place around the construction zones on Chesterfield Rd through Spring St and Dimock St and possibly Reservoir Rd, Main Street Leeds and Spring Street.
  • The project includes replacement of the water line, drainage improvements and reconstruction of the roadway.

Downtown Paving – Pleasant Street, Hampton Avenue, Wright Avenue, Cooke Avenue and Fulton Avenue
  • Warner Brothers LLC and their subcontractor Caracas Construction Corp. will be start work on drainage improvements for Hampton Ave and Wright Ave this week. Traffic on these streets may be restricted to one lane at times, expect some delays.
  • The project includes re-paving of Hampton Avenue, Wright Avenue, Cooke Avenue, Fulton Avenue and Pleasant Street (from Main Street to Hockanum Road).
North Main and Park Street
  • On Tuesday, Quality Markings will be striping centerline and edge lines on several short sections of these roadways that were recently milled and overlaid.
Pleasant Street
  • Columbia Gas will be installing new gas services on Pleasant Street. Motorists should EXPECT DELAYS and seek alternate routes if possible. The work is anticipated to take several months to complete.
Clement Street Bridge
  • N.E.L. Corporation will continue installing temporary truss supports and replacing lower truss chord truss members. Anticipated project completion is in September. Actual reopening of the bridge will depend on MassDOT approval of the completed work.
  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction.

Tuesday, August 7, 2018

Temporary Street Closure on Munroe Street

Effective immediately, the Department of Public Works will be closing Munroe Street, between South Street and East Street, due to a water main break on Tuesday, August 7, 2018.

It is anticipated that the road will be closed until approximately 8pm this evening or until the Water Division completes the repair.

Thank You

Friday, August 3, 2018

Week of 8-6-18 Weather Permitting

For the week of 8-6-18 Weather Permitting

Pothole Update
  • This week the DPW crews repaired potholes on Norfolk Avenue, Cosmian Avenue, Chestnut Street, Pine Brook Curve, Birch Lane, North Elm Street, Fair Street Extension, Burt's Pit Road Extension, Cooke Avenue, and Orchard Avenue. Sidewalk repair was also done on Florence Road as well as work on the Bike Path from State Street to Florence Center.
  • The largest potholes are filled first to alleviate hazards to motor vehicles. As hazards arise and are identified they will be addressed. To report a pothole please visit: http://northamptonma.gov/requesttracker.aspx 
Hinckley Street
  • Ludlow Construction will continue working on the full length of Hinckley Street this week, from South Main Street to Riverside Drive, also including the intersections of South Main Street, Nonotuck Street, Winslow Avenue, Warner Street and Riverside Drive. This work includes construction of sidewalks, driveways, and Wheel Chair Ramps. 
Chesterfield Road at Kennedy Road - Upper Roberts Meadow Reservoir Dam
  • SumCo Eco-Contracting, LLC has removed approximately 20 vertical feet of the dam with approximately 10 vertical feet remaining to be removed. Additional removal of the dam will not occur until after rain events mobilize sufficient sediment in the impoundment downstream. SumCo will be on site to monitor sediment movement weekly and after rain events but has otherwise demobilized from the site.
  • The project will remove the Upper Roberts Reservoir Dam to restore the Roberts Meadow Brook stream channel to its natural course.
Chesterfield Road - Spring Street to Shepards Hollow Road 
  • Palmer Paving, through their subcontractor CNA, will continue installing water and drainage works.
  • Detours will be in place around the construction zones from Chesterfield Rd and Spring St through Dimock St and possibly Reservoir Rd, Main Street Leeds and Spring Street.
  • The project includes replacement of the water line, drainage improvements and reconstruction of the roadway.
Downtown Paving – Pleasant Street, Hampton Avenue, Wright Avenue, Cooke Avenue and Fulton Avenue 
  • Warner Brothers LLC will commence work this coming week by setting up temporary traffic signs on Thursday and Friday. The work may also include temporary street markings on Hampton Avenue and Wright to layout some of the upcoming work.
  • We anticipate that drainage work will begin the following week (August 13- 17) on Hampton Avenue and Wright Avenue. Traffic on these streets may be restricted to one lane at times, expect some delays.
  • The project includes re-paving of Hampton Avenue, Wright Avenue, Cooke Ave. and Fulton Avenue and Pleasant Street (from Main Street to Hockanun Road).
North Main and Park Street 
  • On Thursday, Quality Markings will be striping centerline and edge lines on several short sections of these roadways that were recently milled and overlaid.
Pleasant Street 
  • Columbia Gas will be installing new gas main and services on Pleasant Street between Main Street and Hampton Avenue. Motorists should EXPECT DELAYS and seek alternate routes if possible. The work is anticipated to take several months to complete.
Clement Street Bridge 
  • N.E.L. Corporation has installed staging access and will be installing temporary truss supports so that lower chord truss members can be replaced. Anticipated project completion is in early September. Actual reopening of the bridge will depend on MassDOT approval of the completed work.
  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction. 
Rocky Hill Road (Route 66) - Drain Repair opposite entrance to House of Corrections 
  • Geeleher Enterprises will begin work on Monday (8/6) to repair two drain outlets on the south side of Rocky Hill Road. This work is adjacent to the roadway. Traffic may see minor delays due to trucks pulling off or onto the roadway. 


Friday, July 27, 2018

For the week of July 30, 2018 Weather Permitting

Pothole Update - 


·         This week the DPW crews cleaned catch basins in the city to prevent street flooding.  Clean up efforts were underway because of tree damage caused by the storms.  Next week the crews will continue street sweeping efforts in Ward 7 and potholes repairs will be prioritized.

Hinckley Street -


·         Ludlow Construction will be working on the full length of Hinckley Street this week, from South Main Street to Riverside Drive, also including the intersections of South Main Street, Nonotuck Street, Winslow Avenue, Warner Street and Riverside Drive. This work includes construction of sidewalks, driveways, and Wheel Chair Ramps

Chesterfield Road at Kennedy Road - Upper Roberts Meadow Reservoir Dam

  • SumCo Eco-Contracting, LLC has removed approximately 20 vertical feet of the dam with approximately 10 vertical feet remaining to be removed. Additional removal of the dam will not occur until after rain events mobilize sufficient sediment in the impoundment downstream. SumCo will be on site to monitor sediment movement weekly and after rain events but has otherwise demobilized from the site.
  • The project will remove the Upper Roberts Reservoir Dam to restore the Roberts Meadow Brook stream channel to its natural course. 
Chesterfield Road

  • Palmer Paving, through their subcontractor CNA, will continue installing water and drainage works.
  • Detours will be in place around the construction zones from Chesterfield Rd and Spring St through Dimock St and possibly Reservoir Rd, Main Street Leeds and Spring Street
  • The project includes replacement of the water line, drainage improvements and reconstruction of the roadway.
Pleasant Street
  • Columbia Gas will be installing new gas main and services on Pleasant Street between Main Street and Hampton Avenue. Motorists should EXPECT DELAYS and seek alternate routes if possible. The work is anticipated to take several months to complete.
Clement Street Bridge
  • N.E.L. Corporation has installed staging access and will be installing temporary truss supports so that lower chord truss members can be replaced.  Anticipated project completion is in early September. Actual reopening of the bridge will depend on MassDOT approval of the completed work.

  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction.

Friday, July 20, 2018

For the Week of July 23, 2018, Weather Permitting

For the week of July 23, 2018 Weather Permitting

Pothole Update - 
  • This week the DPW crews repaired the potholes on Old Springfield Road , Wright Avenue and Gleason Road.  They are in the process of repairing the sidewalk on Flore  The largest potholes are being filled first to alleviate hazards to motor vehicles.  As hazards arise and are identified they will be addressed. 
  • To report a pothole please visit: http://northamptonma.gov/requesttracker.asp
  • Street Sweeping is in process in Ward 7.
Hinckley Street -

·         Ludlow Construction will be working on the full length of Hinckley Street this week, from South Main Street to Riverside Drive, including work at the intersections of South Main Street, Nonotuck Street, Winslow Avenue, Warner Street and Riverside Drive. This work includes construction of sidewalks, driveways, and Wheel Chair Ramps.
Chesterfield Road at Kennedy Road - Upper Roberts Meadow Reservoir Dam


·         SumCo Eco-Contracting, LLC has removed approximately 20 vertical feet of the dam with approximately 10 vertical feet remaining to be removed. Additional removal of the dam will not occur until after rain events mobilize sufficient sediment in the impoundment downstream. SumCo will be on site to monitor sediment movement weekly and after rain events but has otherwise demobilized from the site.

·        The project will remove the Upper Roberts Reservoir Dam to restore the Roberts Meadow Brook stream channel to its natural course.
Chesterfield Road
·         Palmer Paving, through their subcontractors, will begin the installation of water and drainage works.
·        Detours will be inplace around the construction zones utilizing Spring Street and Dimock St.

·      The project includes replacement of the water line, drainage improvements and reconstruction of the roadway.
Pleasant Street
  • Columbia Gas will be installing new gas main and services on Pleasant Street between Main Street and Hampton Avenue. Motorists should EXPECT DELAYS and seek alternate routes if possible. The work is anticipated to take several months to complete.
Clement Street Bridge
  •  N.E.L. Corporation has installed staging access and will be installing temporary truss supports so that lower chord truss members can be replaced.  Anticipated project completion is in early September. Actual reopening of the bridge will depend on MassDOT approval of the completed work.
  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction. 

Friday, July 13, 2018

Week of July 16 Weather Permitting

For the week of July 16, 2018 Weather Permitting

Pothole Update - 
  • This week the DPW crews repaired the potholes on Fair Street Extension, Texas Road, Service Center Way, Norwood Avenue and Gleason Road.  The largest potholes are being filled first to alleviate hazards to motor vehicles.  As hazards arise and are identified they will be addressed. 
  • To report a pothole please visit: http://northamptonma.gov/requesttracker.asp
  • Street Sweeping is in process in Ward 7.
Hinckley Street -
  • Ludlow Construction will be working on the full length of Hinckley Street this week from South Main Street to Riverside Drive, including work at the intersections of South Main Street, Nonotuck Street, Maplewood Terrace, Winslow Avenue, Warner Street and Riverside Drive. This work includes the excavation and construction of sidewalk and driveways.
Chesterfield Road at Kennedy Road - Upper Roberts Meadow Reservoir Dam
  • SumCo Eco-Contracting, LLC has removed approximately 20 vertical feet of the dam with approximately 10 vertical feet remaining to be removed. Additional removal of the dam will not occur until after rain events mobilize sufficient sediment in the impoundment downstream. SumCo will be on site to monitor sediment movement during rain events but has otherwise demobilized from the site until those events occur.
  • The project will remove the Upper Roberts Reservoir Dam to restore the Roberts Meadow Brook stream channel to its natural course. 
Chesterfield Road
  • Palmer Paving, through their subcontractors, shall be installing tree protection measures, and beginning the installation of water and drainage works.
  • The project includes replacement of the water line, drainage improvements and reconstruction of the roadway.
Elm Street/West Street
  • On Wednesday, July 18th, Shawmut Design will be coordinating an all-day concrete pour for the Neilson Library project. Concrete trucks will continuously be entering and leaving the site at the signalized crosswalk entrance to Smith. Trucks will be coming up Conz Street from Exit 18, turning onto New South Street and staging at the old horse arena at the corner of West and Earle Streets before being called to the site for delivery. Motorists should anticipate DELAYS and, if possible, SEEK ALTERNATE ROUTES.  
Pleasant Street
  • Columbia Gas will be installing new gas main and services on Pleasant Street between Main Street and Kirkland Avenue. Motorists should EXPECT DELAYS and seek alternate routes if possible. The work is anticipated to take several months to complete.
Clement Street Bridge
  • N.E.L. Corporation will be installing staging platforms and temporary truss supports so that lower chord truss members can be replaced.  Anticipated project completion is in early September. Actual reopening of the bridge will depend on MassDOT approval of the completed work.
  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction. 

Friday, July 6, 2018

The week of July 9, 2018 Weather Permitting

For the week of July 9, 2018 Weather Permitting

Pothole Update - 
  • This week the DPW crews repaired the potholes on Redford Drive, Brookside Circle, Lincoln Avenue, Vernon Street and Cross Path Road.  They are in the process of working on potholes at Ventures Field Road, Henry Street, Mont View Drive, and Valley Road. The largest potholes are being filled first to alleviate hazards to motor vehicles.  As hazards arise and are identified they will be addressed. 
  • To report a pothole please visit: http://northamptonma.gov/requesttracker.asp
Hinckley Street 
  • Ludlow Construction will be working on the full length of Hinckley Street this week, from South Main Street to Riverside Drive, including work at the intersections of South Main Street, Nonotuck Street, Maplewood Terrace, Winslow Avenue, Warner Street and Riverside Drive. This work includes the installation of curbing, raising of utility structures, excavation and construction of sidewalk and driveways.  
  • New sidewalk, a raised crosswalk in Nonotuck Street and final paving are upcoming this summer.
Chesterfield Road at Kennedy Road - Upper Roberts Meadow Reservoir Dam

  • SumCo Eco-Contracting, LLC will be making the third notch in the dam and removing more of the spillway following sediment that was mobilized during the heavy rains on June 28th.
  • The project will remove the Upper Roberts Reservoir Dam to restore the Roberts Meadow Brook stream channel to its natural course. 
Chesterfield Road
  • Palmer Paving, through their subcontractors, shall be installing tree protection Measures..
  • The project includes replacement of the water line, drainage improvements and reconstruction of the roadway.
Pleasant Street
  • Columbia Gas will be installing new gas main on Pleasant Street between Main Street and Kirkland Avenue. Motorists should EXPECT DELAYS and seek alternate routes if possible. The work is anticipated to take several months to complete.
Clement Street Bridge
  • Repair work for the Clement Street Bridge has been awarded to N.E.L. Corporation. Staging has been mobilized to the site and the contractor is awaiting completion of steel fabrication. Anticipated project completion and bridge re-opening is late summer 2018.
  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction which is anticipated to begin the week of July 16th.

Friday, June 29, 2018

For the Week of July 2, 2018 Weather Permitting

For the week of July 2, 2018 Weather Permitting

Pothole Update - 
  • This week the DPW crews repaired the potholes on Overlook Drive, Brookside Drive, Round Hill Road, Henshaw Avenue, Strawberry Hill, Kimball Street, Howe Street.  They are in the process of working on potholes on Sheffield Lane and others throughout the city.  The largest potholes are being filled first to alleviate hazards to motor vehicles.  As hazards arise and are identified they will be addressed. 
  • To report a pothole please visit: http://northamptonma.gov/requesttracker.asp
Hinckley Street 
  • Ludlow Construction will not be working this week.  They will return on Monday, July 9th , to work on installation of curbing, and raising of utility structures.   Driveway and sidewalk construction may also begin that week.
  • New sidewalk, a raised crosswalk in Nonotuck Street and final paving are upcoming this summer.
Main Street Florence
  • Paving of the milled roadway section in front of the new Cumberland Farms is scheduled to occur on Monday, July 2nd. One way traffic will be maintained, but motorists should EXPECT DELAYS and seek alternate routes, if possible. 
Chesterfield Road at Kennedy Road - Upper Roberts Meadow Reservoir Dam
  • SumCo Eco-Contracting, LLC has removed slightly less than one half of the dam. They have demobilized form the site until rain events mobilize some of the sediment in the impoundment downstream.
  • The project will remove the Upper Roberts Reservoir Dam to restore the Roberts Meadow Brook stream channel to its natural course.
Chesterfield Road
  • Palmer Paving is scheduled to be working this week.
  • The project includes replacement of the water line, drainage improvements and reconstruction of the roadway.
Pleasant Street
  • Columbia Gas will be installing new gas main on Pleasant Street between Main Street and Kirkland Avenue. Motorists should EXPECT DELAYS and seek alternate routes if possible. The work is anticipated to take several months to complete.
Clement Street Bridge
  • Repair work for the Clement Street Bridge has been awarded to N.E.L. Corporation. Project submittals are currently under review. Anticipated project completion and bridge re-opening is late summer 2018.
  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction which is anticipated to begin the week of July 9th.

Friday, June 22, 2018

For the week of June 25, 2018 Weather Permitting

For the week of June 25, 2018 Weather Permitting

Pothole Update - To be updated Monday
  • This week the DPW crews repaired the potholes on Grove Street, Island Road, Brookside Circle, Overlook Drive, High Meadow, and Rural Lane.  They are in the process of working on potholes on Acrebrook Drive and Cross Street.  The largest potholes are being filled first to alleviate hazards to motor vehicles.  As hazards arise and are identified they will be addressed. 
  • To report a pothole please visit: http://northamptonma.gov/requesttracker.asp
Hinckley Street 
  • Ludlow Construction will continue with roadway reconstruction this week on Hinckley Street.  DRIVEWAY ACCESS WILL BE LIMITED DURING WORK HOURS, plan to move your vehicle(s) out of your driveway prior to 7:00 AM. This work entails raising covers for manholes & catchbasins, excavation, soil removal, backfilling, placement and grading of gravel.  The ban on parking along Hinckley Street will continue
  • Weather permitting, Monday will include work along Riverside Drive as well as Hinckley Street.  On Wednesday and Thursday, the binder (first) course of pavement will be installed on Hinckley Street. This will be followed by work on sidewalks, curbs, and driveways in following weeks.  
  • Horizontal alignment stakes have been installed along properties at Hinckley Street. 
  • Traffic on Hinckley Street will be restricted and detours may be in place.  Public Safety officer(s) will be on duty.
  • The work of replacement of water and sewer utilities is complete.  New sidewalk, repaving, and a raised crosswalk in Nonotuck Street is upcoming this summer.
Chesterfield Road at Kennedy Road - Upper Roberts Meadow Reservoir Dam
  • SumCo Eco-Contracting, LLC has removed slightly less than one half of the dam. They have demobilized form the site until rain events mobilize some of the sediment in the impoundment downstream.
  • The project will remove the Upper Roberts Reservoir Dam to restore the Roberts Meadow Brook stream channel to its natural course. 
 Chesterfield Road
  • Palmer Paving is scheduled to mobilize for the reconstruction of lower Chesterfield Road.  They will be installing construction signs and sediment controls.
  • The project includes replacement of the water line, drainage improvements and reconstruction of the roadway.
Pleasant Street
  • Columbia Gas will be installing new gas main on Pleasant Street between Main Street and Kirkland Avenue. Motorists should EXPECT DELAYS and seek alternate routes if possible. The work is anticipated to take several months to complete.
Clement Street Bridge
  • Repair work for the Clement Street Bridge has been awarded to N.E.L. Corporation. Project submittals are currently under review. Anticipated project completion and bridge re-opening is summer 2018.
  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction which is anticipated to begin the week of July 9th.

Thursday, June 21, 2018

Hinckley STreet

Hinckley Street Update
  • The Northampton Police Department has posted No Parking signs for the entire length of Hinckley Street during grading and initial paving operations. Cars parked on Hinckley Street between the hours of 7:00 AM - 4:00 PM will be towed beginning Friday, June 22, 2018.  We anticipate grading and initial paving operations to last through June 29, 2018 at 4:00 PM. Access for emergency vehicles will be maintained.