Thursday, May 31, 2018

Week of June 4, 2018 Weather Permitting

For the week of June 4, 2018 Weather Permitting


Pothole Update
  • This week the DPW crews repaired the potholes on Riverside Drive and Ladd Avenue.  They are in the process of working on multiple utility cuts throughout the City.  The largest potholes are being filled first to alleviate hazards to motor vehicles.  As hazards arise and are identified they will be addressed. 
  • To report a pothole please visit: http://northamptonma.gov/requesttracker.asp
Hinckley Street
  • Ludlow Construction will continue to install drainage infrastructure in the Outfall Area below Riverside Drive and possibly crossing Riverside Drive near Hinckley Street.  This work entails excavation, pipe and manhole installation, backfilling, and grading.
  • Traffic on Riverside Drive and Hinckley Street will be restricted and detours will be in place.  Public Safety officer(s) will be on duty.
  • The work of replacement of water and sewer utilities is complete.  New sidewalk, roadway reconstruction and repaving, and a raised crosswalk in Nonotuck Street is upcoming this summer.
Chesterfield Road at Kennedy Road - Upper Roberts Meadow Reservoir Dam
  • SumCo Eco-Contracting, LLC will be establishing access off of Chesterfield Road an making the initial notch for dam removal.
  • The project will remove the Upper Roberts Reservoir Dam to restore the Roberts Meadow Brook stream channel to its natural course. 
Pleasant Street
  • Columbia Gas will be installing new gas main on Pleasant Street between Main Street and Kirkland Avenue. Motorists should EXPECT DELAYS and seek alternate routes if possible. The work is anticipated to take several months to complete.
Clement Street Bridge
  • Repair work for the Clement Street Bridge has been awarded to N.E.L. Corporation. Project submittals are currently under review. Anticipated project completion and bridge re-opening is summer 2018.
  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction which is anticipated to begin in early June.

Friday, May 25, 2018

Week of May 29, 2018 Weather Permitting

For the week of May 29, 2018 Weather Permitting


Pothole Update
  • This week the DPW crews repaired the potholes on Trinity Row, Front Street, Evergreen Street, Villone Drive, and Crosspath Road.  They are in the process of working on Spring Street and Riverside Drive. The largest potholes are being filled first to alleviate hazards to motor vehicles.  As hazards arise and are identified they will be addressed. 
  • To report a pothole please visit: http://northamptonma.gov/requesttracker.asp
Hinckley Street
  • Ludlow Construction will be installing drainage infrastructure in the Outfall Area below Riverside Drive and possibly crossing Riverside Drive beginning Wednesday.  This work entails excavation, pipe and manhole installation, backfilling, and grading.
  • Traffic on Riverside Drive and Hinckley Street will be restricted and detours may be in place.  Public Safety officers will be on duty.
  • The work of replacement of water and sewer utilities is complete.  New sidewalk, roadway reconstruction and repaving, and a raised crosswalk in Nonotuck Street is upcoming this summer.
Chesterfield Road at Kennedy Road - Upper Roberts Meadow Reservoir Dam
  • SumCo Eco-Contracting, LLC will be installing erosion and sedimentation controls, continue with selective clearing and establishing an access road.
  • The project will remove the Upper Roberts Reservoir Dam to restore the Roberts Meadow Brook stream channel to its natural course. 
Pleasant Street
  • Columbia Gas will be installing new gas main on Pleasant Street between Main Street and Kirkland Avenue. Motorists should EXPECT DELAYS and seek alternate routes if possible. The work is anticipated to take several months to complete.
Clement Street Bridge
  • Repair work for the Clement Street Bridge has been awarded to N.E.L. Corporation. Project submittals are currently under review. Anticipated project completion and bridge re-opening is summer 2018.
  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction which is anticipated to begin in early June.

Friday, May 18, 2018

The week of May 21, 2018

For the week of May 21, 2018 Weather Permitting


Pothole Update
  • This week the DPW crews repaired the potholes on North Loudville Road, Drury Lane, and Florence Street.  They are in the process of working on Elm Street. The largest potholes are being filled first to alleviate hazards to motor vehicles.  As hazards arise and are identified they will be addressed. 
  • To report a pothole please visit: http://northamptonma.gov/requesttracker.asp
·       Hinckley Street

  • Ludlow Construction, working with their subcontractor, H.B. Fleming of South Portland Maine, will be installing pre-cast concrete lagging panels for the Pile and Lagging retaining wall below Riverside Drive beginning Monday.  This work also entails excavation, backfilling, and grading. Ludlow Construction may also do some drainage work in the Outfall Area, below Riverside Drive, and possibly crossing Riverside Drive.
  • Traffic on Riverside Drive and Hinckley Street will be restricted and detours may be in place.  Public Safety officer(s) shall be on duty.
  • The work of replacement of water and sewer utilities is complete.  New sidewalk, roadway reconstruction and repaving, and a raised crosswalk in Nonotuck Street is planned for this summer.
Chesterfield Road at Kennedy Road - Upper Roberts Meadow Reservoir Dam
  • SumCo Eco-Contracting, LLC will begin mobilizing equipment, surveying for layout and installing fencing and erosion control measures at the site.
  • The project will remove the Upper Roberts Reservoir Dam to restore the Roberts Meadow Brook stream channel to its natural course. 
Pleasant Street
  • Columbia Gas will be installing new gas main on Pleasant Street between Main Street and Kirkland Avenue. Motorists should EXPECT DELAYS and seek alternate routes if possible. The work is anticipated to take several months to complete
Day Avenue, North Maple Street & North Farms Road
  • Caracas Construction will taking care of punch list items on Day Avenue, North Maple Street ad North Farms Road.
Clement Street Bridge
  • Repair work for the Clement Street Bridge has been awarded to N.E.L. Corporation. Project submittals are currently under review. Anticipated project completion and bridge re-opening is summer 2018.
  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction which is anticipated to begin in early June.

Friday, May 11, 2018

For the week of May 14, 2018 Weather Permitting


Pothole Update
  • This week the DPW crews repaired the potholes Arch Street, Upper Chesterfield Road and Reservoir Road.  They are in the process of working on Loudville Road, North Loudville Road and Florence Street and Main Street in Leeds. The largest potholes are being filled first to alleviate hazards to motor vehicles.  As hazards arise and are identified they will be addressed. 
  • To report a pothole please visit: http://northamptonma.gov/requesttracker.asp
·       Hinckley Street
  • Ludlow Construction, working with their subcontractor, H.B. Fleming of South Portland Maine, will be installing pre-cast concrete lagging panels for the Pile and Lagging retaining wall below Riverside Drive beginning Tuesday or Wednesday. This work also entails excavation, backfilling, and grading.
  • Lulow Construction will also do some remaining drainage work, including installing subdrain, between Warner Street and Maplewood Terrace; and two catch basins near the bottom of Maplewood Terrace.
  • Traffic on Riverside Drive and Hinckley Street will be restricted and detours may be in place.  Public Safety officer(s) shall be on duty.
  • The work of replacement of water and sewer utilities is complete, and the installation of drainage utility continues, but not this week.  A new drainage outfall off Riverside Drive, new sidewalk, roadway reconstruction and repaving, and a raised crosswalk across Nonotuck Street is upcoming this summer.
Chesterfield Road at Kennedy Road - Upper Roberts Meadow Reservoir Dam
  • SumCo Eco-Contracting, LLC will begin mobilizing equipment, surveying for layout and installing fencing and erosion control measures at the site.
  • The project will remove the Upper Roberts Reservoir Dam to restore the Roberts Meadow Brook stream channel to its natural course. 
Pleasant Street
  • Columbia Gas will be installing new gas main on Pleasant Street between Main Street and Kirkland Avenue. Motorists should EXPECT DELAYS and seek alternate routes if possible. The work is anticipated to take several months to complete
Massasoit Street and Woodlawn Avenue
  • Columbia Gas has subcontracted to Precise Paving to mill and overlay Massasoit Street from Arlington Street to Prospect Street, Massasoit Avenue and Woodlawn Avenue near the intersection with Prospect Street. Work will begin on Monday. Motorists should EXPECT DELAYS and seek alternate routes if possible.   
Day Avenue, North Maple Street & North Farms Road
  • Caracas Construction will be doing final cleanup and restoration on Day Avenue, North Maple Street and North Farms Road.
Clement Street Bridge
  • Repair work for the Clement Street Bridge has been awarded to N.E.L. Corporation. Project submittals are currently under review. Anticipated project completion and bridge re-opening is summer 2018.
  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction which is anticipated to begin in early June.

Friday, May 4, 2018

For the week of May 7, 2018 Weather Permitting


Pothole Update
  • This week the DPW crews repaired the potholes on North Farms Road, Crafts Avenue, East Center Street and are in the process of working on Glendale Road and Florence Street. The largest potholes are being filled first to alleviate hazards to motor vehicles.  As hazards arise and are identified they will be addressed. 
  • To report a pothole please visit: http://northamptonma.gov/requesttracker.asp
·       Hinckley Street
  • Ludlow Construction, through their subcontractor, H.B. Fleming, of South Portland Maine, will be continuing the installation of Sheet Piles for a Pile and Lagging retaining wall below Riverside Drive  A small crew from Ludlow construction will be assisting H.B. Fleming, and performing some stump removal and topsoil removal below the wall construction.
  • Traffic on Riverside Drive and Hinckley Street will be restricted and detours may be in place.  Public Safety officer(s) shall be on duty.
  • The work of replacement of water and sewer utilities is complete; and the installation of drainage utility continues after this week.  A new drainage outfall off Riverside Drive, new sidewalk, roadway reconstruction and repaving, and a raised crosswalk across Nonotuck Street is planned for this summer.
Pleasant and Holyoke Streets 
  • Construction on the new building at 256 Pleasant Street is underway and will continue throughout 2018.
Day Avenue, North Maple Street & North Farms Road
  • Caracas Construction will be doing final cleanup and restoration on Day Avenue, North Maple Street and North Farms Road.
Audubon Road  
  • Borges Construction will be working on final cleanup and restoration.
Clement Street Bridge
  • Repair work for the Clement Street Bridge has been awarded to N.E.L. Corporation. Project submittals are currently under review. Anticipated project completion and bridge re-opening is summer 2018.
  • Pedestrian and bicyclist use of the bridge will be allowed except during active construction which is anticipated to begin in early June.