Wednesday, July 17, 2019

Update for Chesterfield Road, Spring Street, Main Street (Leeds), and Cross Street Paving Project

Chesterfield Road, Spring Street, Main Street (Leeds), and Cross Street Paving Project


  • The City has contracted with Palmer Paving for paving and roadway improvements on Chesterfield Road (Westhampton town line to Kennedy Road), Spring Street (Dimock Street to Col. Lavalley Lane; Meadow Street to Pine Street), Main Street - Leeds (Spring Street to 535 feet northerly at the Mill River bridge), and Cross Street (Florence Road to Bliss Street). The scope of this project includes pavement reclamation, cold in-place recycling, line painting, and drainage improvements.  
  • On Spring Street, drainage installation is ongoing this week.
  • On Cross Street, drainage installation is to begin on Thursday and is to continue through the week.